What is proposed

Health Infrastructure, the NSW Health agency leading the project, put the Review of Environmental Factors (REF) for the Health Hub on exhibition on 20 November. An REF is the planning report a public agency prepares when it can build without a development application. This one was written for Health Infrastructure by the consultancy _planning Pty Ltd, and it names Health Infrastructure as both the proponent and the determining authority (page 8): the agency assesses and approves its own project.

The site is the corner of Dudley Street and Urunga Parade, south of the hospital’s multi-storey car park and west of the main campus across New Dapto Road. Today it holds two single-storey buildings, home to the Domestic and Family Violence and Sexual Assault Service and the Bungora Opioid Treatment Service, and tiered at-grade parking with 68 staff and fleet spaces (pages 5, 9 and 17).

The REF describes an up to eight-storey Health Hub building primarily fronting Urunga Parade, including four basement parking levels, with 6,466.15 square metres of floor space (page 26). It takes services moved out of the main campus, including those in Lawson House, and gives the two existing clinics new rooms; their old buildings are knocked down once they have moved (pages 22, 26 and 28). The opioid treatment clinic gets its own level with a private entry off Dudley Street. The main entrance and drop-off are on Urunga Parade, with patient areas, education and training on the ground level; the three floors above are Agile working spaces / staff offices (page 27). Those three floors are 3,007.75 square metres, 46.5 per cent of the building (3,007.75 divided by 6,466.15). Health Infrastructure’s 18 November release adds that the education space includes the Illawarra Shoalhaven Health Education Centre.

The REF says no new beds come from it. Drawing on the Transport Impact Assessment, it counts 14 more treatment spaces, 20 more patients and 28 more full-time staff (page 41). The cost of the Health Hub on its own is not stated in the REF or on the project page; both give only the precinct’s $220 million, announced in the 2025-26 State Budget.

How big, and how it sits

Because the site falls almost 10 metres from Urunga Parade down to Dudley Street (page 15), the building reads differently from each side. To Urunga Parade and New Dapto Road it is four to five storeys, at most 18.8 metres. To Dudley Street it is an eight (8) storey building, at most 29.9 metres, with the upper floors set back and turned away from the street to keep clear of the helicopter flight paths to the helipad on the car park roof (pages 9, 17, 27, 66 and 68). It sits under the 32-metre height limit in the Wollongong Local Environmental Plan. Its floor space ratio is about 1.82 to 1 (6,466.15 divided by the 3,558 square metre site), above the plan’s 1.5 to 1 control, which the REF says does not apply because no development application is needed (pages 27 and 49).

The REF’s own visual assessment names the people most affected: the single-storey homes on the western side of Dudley Street, facing the site (page 68). A

Exhibit A · from the source

Wollongong Hospital Health Hub REF, page 68: The visual impact of the new building from affected Dudley Street properties would be moderate-high. The key visual impacts relate to its relationship to the low-rise low-density developments with Dudley Street.
Page 68 of the Health Hub Review of Environmental Factors (Final Draft v3, 12 November 2026). Outlined: the rating. The next page says no mitigation measures are needed for visual impact. Open the PDF at page 68 Back to the story

The REF says the views lost from Dudley Street are not of any importance, because those homes already face hospital buildings, and that the street’s western side carries a 16-metre height limit that would allow up to four storeys. It then concludes: No mitigation measures are considered necessary in addressing visual impacts and visual amenity. (page 69). On shadow, it finds the winter shadow falls on Urunga Parade and the lower, back-of-house levels of Wollongong Private Hospital and Wollongong Day Surgery opposite, and no Dudley Street home loses sun (page 79).

Building it: hours, length and noise

Work would start in 2027. Stage 1 (about 34 months, to 2029) clears the car park, removes trees, digs 4 to 8 metres down for the basement levels (13,841 cubic metres of cut) and builds the Health Hub. Stage 2 (about 11 months, in 2030) demolishes the two old clinics once their services have moved, then landscapes the ground (pages 22, 28, 30 and 38). That is the 45 months, 34 plus 11. Construction vehicles would come in from Crown Street via Urunga Parade, and the peak workforce could be 200 to 250 people a day (page 38).

Proposed hours are 7am to 6pm Monday to Friday and 8am to 1pm Saturday, with no work on Sundays or public holidays (page 38). The draft mitigation measures narrow the loudest work: rock excavation machinery and mechanical pile drivers only from 9am to 12pm and 2pm to 5pm on weekdays and 9am to 12pm on Saturdays (Appendix AA, measure C6, page 15).

The noise assessment by Acoustic Studio, the project’s acoustic consultant, finds the homes directly across Dudley Street and Urunga Parade will get construction noise at times up to 12 dB above “Highly Noise Affected” noise levels (i.e. > 75dBA). This may require the provision of respite periods for those residents. (REF page 61). Seventy-five plus 12 is 87 decibels. The REF answers yes to whether any receiver will be affected by noise for more than three weeks (page 61). Its table of predictions for homes shows a higher figure in Stage 2. B

Exhibit B · from the source

Noise and Vibration Impact Assessment, Table 13, construction noise predictions for residential receivers in standard hours: at R2, south of the site (NCA2 1 Uranga Pde), 63 to 87 dB(A) for carpark demolition, excavation and light earthworks in Stage 1, and 66 to 92 dB(A) for demolition of the DFVSAS and OTP buildings in Stage 2
Page 40 of Appendix P, the Noise and Vibration Impact Assessment (Acoustic Studio, 6 November 2026), Table 13, left part. Outlined: receiver R2, south of the site, in Stage 1 car park demolition and excavation (63 to 87) and Stage 2 demolition of the two clinic buildings (66 to 92), in dB(A) over 15 minutes (on a phone, the two cells in order). Open the PDF at page 40 Back to the story

Table 13 puts the top of the Stage 1 range for receiver R2, south of the site, at 87, which matches the 12 dB in the summary. For Stage 2 demolition of the old clinics it gives 92, which is 17 above the 75 threshold (92 minus 75). The nearest home on Dudley Street (R1) tops out at 84 in Stage 1, and at 83 during tree removal. The assessment says its figures assume every machine running for the full 15 minutes, and that in practice levels may be 5 to 15 dB lower (page 39). Hospital neighbours, including Wollongong Private Hospital, are predicted up to 23 dB above their management level (REF page 61; Table 14, page 41).

The remedies are a construction noise and vibration plan once a builder is appointed, hoarding and noise curtains, quieter plant, notice of noisy work and a complaints line (pages 61 and 62). The draft mitigation measures list respite periods among the Feasible acoustic controls or management techniques to be used when undesirable noise impacts are anticipated (measure B42, page 12). No measure fixes a respite schedule for the homes opposite.

Parking, traffic and trees

The Health Hub adds 107 basement spaces joined to the existing multi-storey car park, but the joins cost 47 spaces inside that car park and the 68 at-grade spaces go, so the site ends 8 spaces down (107 minus 47 minus 68). On the street, a new loading dock driveway takes 2 spaces on Dudley Street and a closed driveway gives 1 back on Urunga Parade: 9 fewer in all (pages 29 and 30). Six spaces on Dudley Street near the opioid clinic’s entry would be marked for short-term parking, for people using the service (page 29).

The transport consultant, SCT Consulting, counted 176 spare spaces at peak across the two multi-storey car parks. Take away the 8 lost and the 44 extra demand (24 staff, 20 patients) and 124 are left (176 minus 8 minus 44; REF page 60, Transport Impact Assessment Table 4-7, page 24). Most of that margin is staff parking: Table 4-7 leaves 94 staff spaces and lists 28 for patients and visitors. Its own columns add to 30 for patients and visitors (32 plus 18 minus 20), and the text above it says 29. The assessment notes the staff and public areas are marked by signs, not barriers, so spaces can be moved between them. The building is expected to add 49 vehicle trips in the morning peak and 48 in the evening (page 59).

Seven planted trees come out, including three large camphor laurels, an exotic the REF says is listed as a weed in the Wollongong area. Seventeen go in, a net gain of 10 (17 minus 7), mostly 200-litre native or endemic stock on the eastern half of the site once the old clinics are gone (pages 15 and 32). The site is not heritage listed; the nearest listed item, Elouera House, is 200 to 220 metres away with the main hospital between (page 71). A search of the state Aboriginal heritage register found no recorded sites within 50 metres (page 70). The old clinic buildings contain non-friable asbestos, and the ground under them was not tested because the buildings were in the way; that is to happen during or after demolition (pages 35 and 75).

Our read

This is opinion, built on the documents above.

It is the right kind of first move. It builds on a car park and two single-storey clinics at the campus edge, not on open ground, and gives an opioid treatment service and a family violence and sexual assault service purpose-built rooms. It keeps enough parking overall and ends with more trees than it starts with. Nearly half the floor space is offices, which is less glamorous than the renders suggest, but moving staff and services out of Lawson House is what frees the main campus for the rest of the precinct.

The cost lands on two streets, and the plan does little about it. The REF itself rates the view from the Dudley Street homes moderate-high, then decides no mitigation is needed. The building exceeds the floor space control that would apply to a development application on that land; the REF sets it aside because no application is needed, and the agency approving the project is the agency building it. Across a build of nearly four years, the homes opposite are predicted at times to get noise above the level the assessment itself calls highly noise affected, and respite is something that “may” be required. A promise of fixed quiet periods for Dudley Street and Urunga Parade, written into the final measures, would cost the project little.

The two noise figures should be reconciled before anyone relies on them. The summary says up to 12 dB over the threshold; the table it summarises reaches 17 for the Stage 2 demolition. We asked Health Infrastructure on 26 November which figure residents should rely on, and whether the final measures will commit to respite periods for those homes, and will add its answer here, or say if none arrives.

Submissions are the only outside check. Health Infrastructure says comments received will be addressed in the final REF (page 52). Anyone near the site who wants respite hours, screening on the Dudley Street face or a say on the parking has until 18 December.

How to comment

The REF and its 28 appendices are on the Have your say page, open until 11.59pm on 18 December 2026; the page says submissions will help inform the final design before construction begins in late 2027. Health Infrastructure’s release lists four drop-in sessions: Thursday 3 December, 9am to 11am in the Crown Street entrance foyer and 1pm to 3pm at The Long Shot Café, both at Wollongong Hospital; an online session on Tuesday 8 December, 6pm to 7pm; and Friday 11 December, 8am to 3pm at the Farmers Markets on Crown Street. Questions go to the project team at HI-wollongong@health.nsw.gov.au, the address on the project page.

How we sourced this

We read the Review of Environmental Factors (Final Draft v3, 12 November 2026, 93 pages) end to end, and from its appendices the draft mitigation measures (Appendix AA), the Transport Impact Assessment (Appendix G), the Noise and Vibration Impact Assessment (Appendix P, its summary and Tables 13 and 14), the Engagement Report (Appendix O), the arborist’s report (Appendix B) and the aviation advice (Appendix Z), all as downloaded from the Have your say page on 26 November 2026. We also read the project page and Health Infrastructure’s 18 November release. Page numbers are each document’s own printed numbers. Every computed figure shows its sum in the text. The noise figures are the consultant’s predictions, not measurements. We asked Health Infrastructure on 26 November about the two noise figures and respite periods. The section headed Our read is opinion.

Sources

How we did it. AI did the heavy reading and the first draft; people own what it says. Built from the primary sources below. 8 quotations were machine-checked, character by character, against our archived copies. Read our method.

  1. Health Infrastructure (prepared by _planning Pty Ltd), Review of Environmental Factors, Wollongong Hospital Health Hub, Final Draft v3, 12 November 2026, read 26 November 2026 (pages 5, 8, 9, 15, 17, 22, 26 to 30, 32, 35, 38, 41, 49, 52, 59 to 62, 66, 68 to 71, 75 and 79). Shown in Exhibit A.
  2. Acoustic Studio for Health Infrastructure, Noise and Vibration Impact Assessment for Review of Environmental Factors (Appendix P), 6 November 2026, read 26 November 2026 (pages 39 and 40, Table 13). Shown in Exhibit B.
  3. Health Infrastructure, Recommended (Draft) Mitigation Measures (Appendix AA), 10 November 2026, read 26 November 2026 (measure B42, page 12; measure C6, page 15); and SCT Consulting, REF Transport Impact Assessment (Appendix G), 6 November 2026, read 26 November 2026 (Table 4-7, page 24).
  4. NSW Government, Have your say: Wollongong Hospital and Health Precinct Health Hub Review of Environmental Factors, and the Wollongong Hospital and Health Precinct project page (last updated 20 November 2026), both read 26 November 2026.
  5. Health Infrastructure, First look at new Health Hub design for Wollongong Hospital and Health Precinct, 18 November 2026, read 26 November 2026.

Spotted an error, or read these documents differently? Tell us and we will check it against the documents and log the outcome here.